The Transmission Company of Nigeria (TCN) has received funds from the Federal Ministry of Power and Housing for the electrification of the Loko community of Nassarawa State and Agatu community in Agatu local government area of Benue State.
TCN now invites bids from interested bidders for the supply and installation of equipment and material for the electrification project.
Lot 1 – supply and installation of materials for 30km route length of 33kV lines with its associated 2No. 500HVA, 33kV/415kV overheard line in Loko community.
Lot 2 – supply and installation of material for 8km of 33kV line with its associated 1No. 500KVA, 33/0.415kV transformer substations, and 2km of 0.415kV overhead line in Oweto-Agatu community.
Source:Â ESI Africa