Guinea, Shareholders Agree JV Terms on Simandou Iron Ore

Guinean authorities and shareholders have agreed on the terms of a joint venture to mine Simandou, one of the world’s largest deposits of iron ore, paving the way for work to resume this month, the presidency said on Monday.

Guinea’s transitional government ordered work to stop last July to try to force the shareholders – which include Rio Tinto (RIO.L), (RIO.AX), Aluminium Corporation of China (Chinalco), China Baowu Steel (Baowu), and Winning Consortium Simandou (WCS) – to agree on joint venture terms.

At the time, authorities said they needed clarification on how the West African country’s interests would be preserved as the companies tap into Simandou’s more than 4 billion tonnes of ore.

All parties signed a shareholder pact for the La Compagnie du TransGuinéen (CTG) joint venture on March 8, marking a “crucial step” in negotiations between the Guinean state and industrial partners, the presidency said in a statement dated March 8, but tweeted on Monday.

The CTG guarantees the government 15% of the Simandou iron ore as well as a free and non-dilutable 15% stake in railway and port infrastructure.

It also reaffirms previously-stated commitments to eventually open the railway to passenger services and other users.

“Today marks the most important date in the development of the Simandou project,” WCS representative Robin Lu said after the signing ceremony, which was broadcast on state television late on Sunday.

The Simandou project has been haggled over for years, its exploitation delayed by legal wrangling and the difficulty and cost of building infrastructure.

Rio Tinto representative Lawrence Dechambenoit said the Simandou project had never come so close to fruition.

Under the CTG, Rio Tinto will finance half the project, which has an estimated cost of between $15 billion and $20 billion. WCS will cover the other half.

Baowu’s representative in Conakry, Yang Gongyang, said the CTG was “an important step for the Simandou project”.

The minister in charge of the presidency’s cabinet, Djiba Diakite, said he was confident different viewpoints would converge and called on all the industrial partners to take necessary steps to ensure work resumes this month as planned.

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Newsletter

Get to read our latest stories right in your email

Show some Love. Share this post

Copyright 2022. All rights reserved. This material, and other digital content on this website, may not be reproduced, published, broadcast, rewritten or redistributed in whole or in part without prior express written permission from Majorwaves Energy Report

Show Buttons
Hide Buttons