Electricity: GenCos fail to generate 3,060.5 megawatts due to gas shortage
– By majorwavesen

Follow us on:

This information was made known in a daily energy report by the Advisory Power Team, office of the Vice President, a copy of which was obtained  in Abuja on Tuesday .

The report also noted that 222.5 megawatts of electricity was not generated due to unavailability of transmission infrastructure during the period.

Similarly, it said that 182 megawatts was not generated due to high frequency resulting from unavailability of distribution infrastructure.

The report, however, said that the GenCos released an average of 4,091 MegaWatts/Hour of electricity into the national grid on Monday.

It said the electricity sent out by the GenCos was down by 4.74 megawatts from the 4,096 megawatts released on Sunday.

The report revealed that the power sector lost an estimated N1.7 billion on Monday due to insufficient gas supply, distribution and transmission infrastructure.

On sector reform and activities, it said that the dominant constraint for Monday was unavailability of gas.

The report said that the peak generation attained was 4,884 megawatts.

 

Your subscription could not be saved. Please try again.
Your subscription has been successful.

Newsletter

Get to read our latest stories right in your email

Show some Love. Share this post

Copyright 2022. All rights reserved. This material, and other digital content on this website, may not be reproduced, published, broadcast, rewritten or redistributed in whole or in part without prior express written permission from Majorwaves Energy Report

Show Buttons
Hide Buttons