Nigeria’s oil and gas sector is set to record another milestone as the $3.3 billion Floating Production Storage Offloading (FPSO) unit built by Samsung Heavy Industries of Korea (SHI) for the 200,000 barrels per day capacity Egina oilfield will sail away in the early hours of today (Sunday) from LADOL Free Zone in Lagos to the offshore field, investigation has revealed.
It was gathered that with the successful completion of the fabrication and integration works in Lagos, the FPSO will in three days’ time arrive at the Egina oilfield located in Oil Mining Lease (OML) 130, which is being developed at the cost of $16 billion by the French oil major, Total.
The FPSO sailed away from the quayside at Samsung Yard in Geoje, South Korea on October 31, 2017 and arrived at the Samsung Yard (SHI-MCI FZE quayside) in LADOL free zone in Lagos in January, where it was integrated locally by Samsung Heavy Industries Nigeria (SHIN) Limited.
Source: THISDAY